[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100208,779,1,"单选题","施工合同中，不可预见物质条件的风险由发包人承担，承包人遇到不可预见物质条件时，及时通知了监理人，监理人没有发出指示，承包人因采取合理措施而增加的费用和工期延误，由( )承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","监理人",{"key":23,"text":24,"correct":18},"D","发包人和承包人","2020版教材P108-110 承包人遇到不利物质条件时，应采取适应不利物质条件的合理措施继续施工，并通知监理人。监理人应当及时发出指示，构成变更的，按变更对待。如果监理人没有发出指示，承包人因采取合理措施而增加的费用和工期延误，仍由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]