[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100195,779,1,"单选题","施工阶段承包人按合同约定完成了包括缺陷责任期内的全部承包工作后，发包人应付给承包人的金额称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":18},"B","合同价格",true,{"key":20,"text":21,"correct":14},"C","估算价",{"key":23,"text":24,"correct":14},"D","质量保证金","2020版教材P104-107 本题考核的是合同价格。合同价格指承包人按合同约定完成了包括缺陷责任期内的全部承包工作后，发包人应付给承包人的金额。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]