[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100193,779,1,"单选题","根据《标准施工合同》，不属于施工合同履行中“不利物质条件”的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不利地质条件",false,{"key":16,"text":17,"correct":18},"B","不利气候条件",true,{"key":20,"text":21,"correct":14},"C","非自然的物质障碍",{"key":23,"text":24,"correct":14},"D","不利水文条件","2020版教材P108-110 本题考核的是不利物质条件。不利物质条件属于发包人应承担的风险，指承包人在施工场地遇到的不可预见的自然物质条件、非自然的物质障碍和污染物，包括地下和水文条件，但不包括气候条件",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]