[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100183":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100183,779,1,"单选题","下列不属于发包人的责任引起暂停施工情况的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人未履行合同规定的义务",false,{"key":16,"text":17,"correct":14},"B","不可抗力",{"key":19,"text":20,"correct":14},"C","协调管理原因",{"key":22,"text":23,"correct":24},"D","季节性大雨引起的停工",true,"2020版教材P99-102 发包人承担合同履行的风险较大，造成暂停施工的原因可能来自于未能履行合同的行为责任，也可能源于自身无法控制但应承担风险的责任。大体可以分为以下几类原因致使施工暂停：(1)发包人未履行合同规定的义务；(2)不可抗力；(3)协调管理原因；(4)行政管理部门的指令。选项D不属于不可抗力的因素。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]