[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100181,779,1,"单选题","由于发包人的原因发生暂停施工的紧急情况，且监理人未及时下达暂停施工指示，承包人可先暂停施工并及时向监理人提出暂停施工的书面请求。监理人应在接到书面请求后的( )h内予以答复，逾期未答复视为同意承包人的暂停施工请求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","24",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","48","2020版教材P99-102 本题考查的是施工进度管理。由于发包人的原因发生暂停施工的紧急情况，且监理人未及时下达暂停施工指示，承包人可先暂停施工并及时向监理人提出暂停施工的书面请求。监理人应在接到书面请求后的24小时内予以答复，逾期未答复视为同意承包人的暂停施工请求 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]