[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100180":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100180,779,1,"单选题","为了保证实际施工过程中承包人能够按计划施工，( )通过协调保障承包人的施工不受到外部或其他承包人的干扰，对已确定的施工计划要进行动态管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人",true,{"key":16,"text":17,"correct":18},"B","发包人",false,{"key":20,"text":21,"correct":18},"C","总包单位",{"key":23,"text":24,"correct":18},"D","设计单位","2020版教材P99-102 本题考查的是施工进度管理。为了保证实际施工过程中承包人能够按计划施工，监理人通过协调保障承包人的施工不受到外部或其他承包人的干扰，对已确定的施工计划要进行动态管理 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]