[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100179,779,1,"单选题","监理人要求的暂停施工的赔偿与责任的说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","停工责任在发包人，由发包人承担所发生的追加合同价款，赔偿承包商由此造成的损失，相应顺延工期",false,{"key":16,"text":17,"correct":14},"B","停工责任在承包人，由承包人承担发生的费用，工期不予顺延",{"key":19,"text":20,"correct":14},"C","暂停施工期间，承包人负责妥善保护工程并提供安全保障",{"key":22,"text":23,"correct":24},"D","停工责任在承包人，由承包人承担发生的费用，相应顺延工期",true,"2020版教材P99-102 本题考查的是施工进度管理。通用条款规定，承包人责任引起的暂停施工，增加的费用和工期由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]