[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100178,779,1,"单选题","承包人未能按照合同计划完成工作时，监理人要求采取措施加快进度，此时承包人( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可以拒绝执行",false,{"key":16,"text":17,"correct":14},"B","应当执行，但可获得费用补偿",{"key":19,"text":20,"correct":14},"C","应当执行，但可获得费用和利润的补偿",{"key":22,"text":23,"correct":24},"D","应当执行，不能获得补偿",true,"2020版教材P99-102 本题考查的是施工进度管理。承包人未能按合同进度计划完成工作时，承包人应采取措施加快进度，并承担加快进度所增加的费用。由于承包人原因造成工期延误，承包人应支付逾期竣工违约金。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]