[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100176,779,1,"单选题","缺陷责任期从( )起算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标函中写明的竣工日开始",false,{"key":16,"text":17,"correct":14},"B","开工通知中写明的开工日开始",{"key":19,"text":20,"correct":14},"C","投标函中写明的开工日开始",{"key":22,"text":23,"correct":24},"D","工程接收证书中写明的竣工日开始",true,"2020版教材P99 缺陷责任期从工程接收证书中写明的竣工日开始起算，期限视具体工程的性质和使用条件的不同在专用条款内约定(一般为一年)。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]