[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100175":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100175,779,1,"单选题","按照建设工程施工合同示范文本的规定，承包人的施工期应为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人开工通知写明的开工日至实际竣工日",true,{"key":16,"text":17,"correct":18},"B","承包人实际开工日至实际竣工日",false,{"key":20,"text":21,"correct":18},"C","监理人开工通知写明的开工日至验收合格日",{"key":23,"text":24,"correct":18},"D","承包人实际开工日至验收合格日","2020版教材P99 承包人施工期从监理人发出的开工通知中写明的开工日起算，至工程接收证书中写明的实际竣工日止。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]