[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100165":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100165,779,1,"单选题","下列关于单位工程竣工验收的说法，不正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单位工程验收合格后，由监理人向承包人出具经发包人签认的单位工程验收证书",false,{"key":16,"text":17,"correct":14},"B","单位工程的验收成果和结论作为全部工程竣工验收申请报告的附件",{"key":19,"text":20,"correct":14},"C","移交后的单位工程由发包人负责照管",{"key":22,"text":23,"correct":24},"D","合同约定了单位工程分部移交，如果发包人在全部工程竣工前，使用已接收的单位工程运行影响了承包人的后续施工，发包人应承担由此增加的费用和(或)工期延误，并支付承包人合理利润",true,"2020版教材P114-117 除了合同约定的单位工程分部移交的情况外，如果发包人在全部工程竣工前，使用己接收的单位工程运行影响了承包人的后续施工，发包人应承担由此增加的费用和(或)工期延误，并支付承包人合理利润",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]