[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100160,779,1,"单选题","根据《标准施工合同》，不可抗力停工期间的照管和后续清理，承包商可索赔( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期和费用",false,{"key":16,"text":17,"correct":14},"B","费用和利润",{"key":19,"text":20,"correct":21},"C","费用",true,{"key":23,"text":24,"correct":14},"D","工期","2020版教材P110-112 停工损失由承包人承担，但停工期间应监理人要求照管工程和清理、修复工程的金额由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]