[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100158,779,1,"单选题","如果索赔事件的影响持续存在，承包商应在该项索赔事件( )，提出最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发生后的28天内",false,{"key":16,"text":17,"correct":14},"B","全部消除后",{"key":19,"text":20,"correct":14},"C","影响结束后的14天内",{"key":22,"text":23,"correct":24},"D","影响结束后的28天内",true,"2020版教材P110-112 本题考查的是索赔管理。对于具有持续影响的索赔事件，承包人应按合理时间间隔陆续递交延续的索赔通知，说明连续影响的实际情况和记录，列出累计的追加付款金额和(或)工期延长天数。在索赔事件影响结束后的 28 天内，承包人应向监理人递交最终索赔通知书，说明最终要求索赔的追加付款金额和延长的工期，并附必要的记录和证明材料。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]