[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100156,779,1,"单选题","根据《标准设计施工总承包合同》，工程实施中应给予承包人延长工期、增加费用并支付合理利润的情形是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不可抗力不能按期竣工",false,{"key":16,"text":17,"correct":18},"B","监理人的指示错误",true,{"key":20,"text":21,"correct":14},"C","不可预见的物质条件",{"key":23,"text":24,"correct":14},"D","异常恶劣的气候条件","2020版教材P110-112 本题考查的是索赔管理。标准施工合同中应给承包人补偿的条款 表6-2中监理人的指示延误或错误指示：工期、费用、利润均可补偿。（教材111页）",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]