[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100154,779,1,"单选题","标准施工合同通用条款规定的变更范围不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","取消合同中任何一项工作",true,{"key":16,"text":17,"correct":18},"B","改变合同中任何一项工作的质量或其他特性",false,{"key":20,"text":21,"correct":18},"C","改变合同工程的基线、标高、位置或尺寸",{"key":23,"text":24,"correct":18},"D","改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序","2020版教材P108-110 标准施工合同通用条款规定的变更范围包括:(1)取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施；(2)改变合同中任何一项工作的质量或其他特性；(3)改变合同工程的基线、标高、位置或尺寸；(4)改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；(5)为完成工程需要追加的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]