[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100152,779,1,"单选题","施工过程中发生变更，而合同中没有适用或类似工程的单价，应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由发包人提出适当的变更工作单价并执行",false,{"key":16,"text":17,"correct":14},"B","由承包人提出适当的变更工作单价，经监理人确认后执行",{"key":19,"text":20,"correct":21},"C","由监理人商定或确定变更工作单价并执行",true,{"key":23,"text":24,"correct":14},"D","由工程造价管理机构提出变更工作单价并执行","2020版教材P108-110 本题考查的是变更管理。已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]