[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100146,779,1,"单选题","如发生了导致承包人增加开支的事件，但却是属于发包人也无法合理预见和克服的情况，则( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","同时补偿费用和利润",false,{"key":16,"text":17,"correct":14},"B","费用和利润均不补偿",{"key":19,"text":20,"correct":21},"C","可以补偿费用但不能补偿利润",true,{"key":23,"text":24,"correct":14},"D","可以补偿利润但不能补偿费用","2020版教材P104-107 本题考查的是工程款支付管理。导致承包人增加开支的事件如果属于发包人也无法合理预见和克服的情况，应补偿费用但不计利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]