[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100144,779,1,"单选题","某施工合同约定钢材由发包人供应，但钢材到货时发包人与监理工程师都没有通知承包人验收，供应商就将钢材卸货于施工现场。在使用前发现钢材数量出现较大短缺，这一钢材损失应由( )承担。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":14},"B","钢材供应商",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","发包人",true,"2020版教材P102-104 发包人提供的材料和工程设备的规格、数量或质量不符合合同要求，或由于发包人原因发生交货日期延误及交货地点变更等情况时，发包人应承担由此增加的费用和(或)工期延误，并向承包人支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]