[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100143,779,1,"单选题","某施工合同履行过程中，隐蔽的工程隐蔽前未通知监理工程师到场检查，后监理工程师要求剥露重新检验。重新检验的结果表明质量合格，则下列关于损失承担的表述中，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人支付发生的全部费用，工期不予顺延",false,{"key":16,"text":17,"correct":14},"B","发包人支付发生的全部费用，工期给予顺延",{"key":19,"text":20,"correct":14},"C","承包人承担发生的全部费用，工期给予顺延",{"key":22,"text":23,"correct":24},"D","承包人承担发生的全部费用，工期不予顺延",true,"2020版教材P102-104 承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖，监理人有权指示承包人钻孔探测或揭开检查，由此增加的费用和(或)工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]