[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100142,779,1,"单选题","某钢筋分项工程的施工具备隐蔽条件，经工程师检查认可后承包人继续施工。后工程师又发出重新剥露检查的指示，承包人执行了该指示。重新检验表明该分项工程存在质量缺陷，承包人修复后再次隐蔽。下列关于承包人的经济损失和工期延误的责任承担的说法中，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期和经济损失均由承包人承担",true,{"key":16,"text":17,"correct":18},"B","给予经济损失补偿，不顺延合同工期",false,{"key":20,"text":21,"correct":18},"C","顺延合同工期，不补偿经济损失",{"key":23,"text":24,"correct":18},"D","补偿经济损失并顺延合同工期","2020版教材P102-104 本题考查的是施工质量管理。监理人对已覆盖的隐蔽工程部位质量有疑问时，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状。经检验证明工程质量符合合同要求，由发包人承担由此增加的费用和(或)工期延误，并支付承包人合理利润；经检验证明工程质量不符合合同要求，由此增加的费用和(或)工期延误由承包人承担 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]