[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100138,779,1,"单选题","在施工合同履行中，发包人按合同约定购买了玻璃，现场交货双方共同清点检验接收后交承包人的仓库保管员保管，当施工需要使用时发现部分玻璃丢失，则应由( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","保管员负责赔偿损失",false,{"key":16,"text":17,"correct":14},"B","发包人承担损失责任",{"key":19,"text":20,"correct":21},"C","承包人负责赔偿损失",true,{"key":23,"text":24,"correct":14},"D","发包人与承包人共同承担损失责任","2020版教材P102-104 本题考查的是对施工质量管理。承包人会同监理人在约定的时间内，在交货地点共同进行验收。发包人提供的材料和工程设备验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]