[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100135,779,1,"单选题","按照标准施工合同通用条款的规定，如果监理人没有在约定时间内对承包人提交的进度计划后予以批复或提出修改意见，则视为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人已批准，对承包人.发包人产生约束力，但监理人不受其约束",false,{"key":16,"text":17,"correct":18},"B","监理人已批准，将作为判定是否顺延合同工期的主要依据",true,{"key":20,"text":21,"correct":14},"C","监理人未批准，承包人应修改进度计划",{"key":23,"text":24,"correct":14},"D","监理人未批准，承包人应等待监理人的进一步指示","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]