[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100134,779,1,"单选题","约定的开工日期已届至但发包人开工前的配合工作未完成，相应的后果责任包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延迟开工，合同工期顺延，赔偿承包人的相应损失",true,{"key":16,"text":17,"correct":18},"B","延迟开工，合同工期不顺延，赔偿承包人的相应损失",false,{"key":20,"text":21,"correct":18},"C","延迟开工，合同工期顺延，无需赔偿承包人的相应损失",{"key":23,"text":24,"correct":18},"D","按时开工，合同工期顺延，赔偿承包人的相应损失","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]