[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100133,779,1,"单选题","某项目监理人于7 月10 日发出开工通知，承包人于7 月11 日收到该通知，通知中说明开工日期为8 月1 日，但因拆迁纠纷直至8 月20 日才具备开工条件，则该项目的开工日期应为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7月10日",false,{"key":16,"text":17,"correct":14},"B","7月11日",{"key":19,"text":20,"correct":14},"C","8月1日",{"key":22,"text":23,"correct":24},"D","8月20日",true,"(3)开工通知发出前，承包人经发包人同意己经实际进场施工的，(无论此后是否发出开工通知)以实际进场施工时间为开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]