[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100129,779,1,"单选题","关于建设工程施工准备阶段的合同管理中，发包人、承包人、监理人各自的义务和职责表述正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","移交施工场地是发包人的义务，必须一次移交完成",false,{"key":16,"text":17,"correct":14},"B","建立完善的质量检查制度是承包人的义务，应在施工场地设置专门的质量检查机构，配备兼职质量检查人员",{"key":19,"text":20,"correct":14},"C","监理人未按时对承包人提出的施工进度计划作出批复或提出修改意见，则该进度计划视为未得到批准",{"key":22,"text":23,"correct":24},"D","监理人征得发包人同意后，应在约定的开工日期7天前向承包人发出开工通知，合同工期自开工通知中载明的开工日起计算",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]