[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100127,779,1,"单选题","某项目承包人经发包人同意于7 月10 日进场施工后，监理人于7 月20 日发出开工通知，承包人于7 月21 日收到该通知，通知中说明开工日期为8 月10 日，则该项目的开工日期应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7月10日",true,{"key":16,"text":17,"correct":18},"B","7月20日",false,{"key":20,"text":21,"correct":18},"C","7月21日",{"key":23,"text":24,"correct":18},"D","8月10日","\"(3)开工通知发出前，承包人经发包人同意己经实际进场施工的，(无论此后是否发出开工通知)以实际进场施工时间为开工日期。 \"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]