[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100126,779,1,"单选题","约定的开工日期已届至，此时发包人开工前的配合工作已完成，但承包人的开工准备还不满足开工条件，则下列说法不正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按时发出开工通知",false,{"key":16,"text":17,"correct":18},"B","合同工期予以顺延",true,{"key":20,"text":21,"correct":14},"C","提前7天向承包人发出开工通知",{"key":23,"text":24,"correct":14},"D","以开工通知中载明的开工日为开工日期","(1)如果约定的开工日期已届至且发包人开工前的配合工作已完成。应委托监理人按专用条款约定的时间向承包人发出开工通知:即使此时承包人的开工准备还不满足开工条件，监理人仍应按时发出开工通知，合同工期不予顺延。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]