[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100125,779,1,"单选题","根据《标准施工招标文件》，“合同进度计划”是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人按监理人指示修改后经发包人批准的进度计划",false,{"key":16,"text":17,"correct":18},"B","承包人按监理人指示修改后经监理人批准的进度汁划",true,{"key":20,"text":21,"correct":14},"C","承包人投标书内提交的进度计划",{"key":23,"text":24,"correct":14},"D","承包人在施工准备阶段编制的进度计划","2020版教材P98-99 监理人对承包人的施工组织设计中的进度计划审查，不仅要看施工阶段的时间安排是否满足合同要求，更应评审拟采用的施工组织、技术措施能否保证计划的实现。监理人审查后，应在专用条款约定的期限内，批复或提出修改意见，否则该进度计划视为已得到批准。经监理人批准的施工进度计划称为\"合同进度计划\"。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]