[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100113,779,1,"单选题","下列关于中标通知书的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","中标通知书是招标人接受中标人的书面承诺文件",false,{"key":16,"text":17,"correct":18},"B","中标价作为该投标人评标的基准价格",true,{"key":20,"text":21,"correct":14},"C","项目经理在要求履行合同时必须到位",{"key":23,"text":24,"correct":14},"D","项目经理的名称可以不是投标文件中说明的人选","2020版教材P92-93 项目经理的名称是中标人的投标文件中说明并已在评标时作为量化评审要素的人选，要求履行合同时必须到位。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]