[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100112,779,1,"单选题","根据《标准施工合同》，施工合同文件包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件",false,{"key":16,"text":17,"correct":18},"B","投标函及投标函附录",true,{"key":20,"text":21,"correct":14},"C","委托监理协议书",{"key":23,"text":24,"correct":14},"D","投标企业定额标准","2020版教材P92-93 合同的组成文件包括：合同协议书；中标通知书；投标函及投标函附录；专用合同条款；通用合同条款；技术标准和要求；图纸；已标价的工程量清单；经合同当事人双方确认构成合同的其他文件。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]