[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100111,779,1,"单选题","根据国家测绘基准、测绘系统和工程测量技术规范以及合同中对工程精度的要求，()负责测设施工控制网。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",true,{"key":16,"text":17,"correct":18},"B","发包人",false,{"key":20,"text":21,"correct":18},"C","监理人",{"key":23,"text":24,"correct":18},"D","勘察人","2020版教材P97-98 本题考查的是承包人的义务。承包人依据监理人提供的测量基准点、基准线和水准点及其书面资料，根据国家测绘基准、测绘系统和工程测量技术规范以及合同中对工程精度的要求，测设施工控制网，并将施工控制网点的资料报送监理人审批。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]