[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100105,779,1,"单选题","根据《标准施工合同》，“合同进度计划”是指( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人投标书内提交的进度计划",false,{"key":16,"text":17,"correct":14},"B","施工准备阶段承包人编制的进度计划",{"key":19,"text":20,"correct":21},"C","承包人按监理人指示修改后经监理人批准的进度计划",true,{"key":23,"text":24,"correct":14},"D","承包人按监理人指示修改后经发包人批准的进度计划","2020版教材P98-99 本题考查的是监理人的职责。经监理人批准的施工进度计划称为“合同进度计划” 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]