[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100103,779,1,"单选题","以下( )专项施工方案，需要进行5人以上专家论证方案的安全性和可靠性。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","高大模板工程",true,{"key":16,"text":17,"correct":18},"B","浅基坑工程",false,{"key":20,"text":21,"correct":18},"C","大爆破工程",{"key":23,"text":24,"correct":18},"D","脚手架工程","2020版教材P97-98 本题考查的是承包人的义务。在施工组织设计中应针对深基坑工程、地下暗挖工程、高大模板工程、高空作业工程、深水作业工程、大爆破工程的施工编制专项施工方案。对于前3项危险性较大的分部分项工程的专项施工，还需经5人以上专家论证方案的安全性和可靠性 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]