[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100102,779,1,"单选题","根据《标准施工合同》，施工准备阶段设计交底应由( )组织。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","总承包人","2020版教材P96-97 本题考查的是发包人的义务。发包人应根据合同进度计划，组织设计单位向承包人和监理人对提供的施工图纸和设计文件进行交底，以便承包人制定施工方案和编制施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]