[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100098":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100098,779,1,"单选题","根据《标准施工合同》，采用公式法调价方式考虑市场价格浮动对合同价的影响，仅适用于工程量清单中的( )部分。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价支付",true,{"key":16,"text":17,"correct":18},"B","工程材料费用",false,{"key":20,"text":21,"correct":18},"C","总价支付",{"key":23,"text":24,"correct":18},"D","人工费用","2020版教材P93-95 标准施工合同通用条款规定用公式法调价，但调整价格的方法仅适用于工程量清单中按单价支付部分的工程款，总价支付部分不考虑物价浮动对合同价格的调整。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]