[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100096,779,1,"单选题","通用条款规定以投标截止日前第28天定义为( )，作用是划分该日后由于政策法规的变化或市场物价浮动对合同价格影响的责任。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基准日期",true,{"key":16,"text":17,"correct":18},"B","下达开工令",false,{"key":20,"text":21,"correct":18},"C","合同签字日",{"key":23,"text":24,"correct":18},"D","风险事件发生日","2020版教材P93-95 本题考查的是订立合同时需要明确的内容。通用条款规定的基准日期指投标截止日前第28天。规定基准日期的作用是划分该日后由于政策法规的变化或市场物价浮动对合同价格影响的责任 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]