[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100092":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100092,779,1,"单选题","按照《建设工程施工合同(示范文本)》规定，当组成施工合同的各文件出现含糊不清或矛盾时，应按( )顺序解释。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同协议书、已标价的工程量清单、中标通知书",false,{"key":16,"text":17,"correct":14},"B","中标通知书、投标书及附件、合同履行中的变更协议",{"key":19,"text":20,"correct":21},"C","合同协议书、中标通知书、已标价的工程量清单",true,{"key":23,"text":24,"correct":14},"D","合同专用条款、合同通用条款、中标通知书","2020版教材P92-93 本题考查的是合同文件。合同文件解释顺序为：(1)合同协议书；(2)中标通知书；(3)投标函及投标函附录；(4)专用合同条款；(5)通用合同条款；(6)技术标准和要求；(7)图纸；(8)已标价的工程量清单；(9)其他合同文件----经合同当事人双方确认构成合同的其他文件。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]