[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100089,779,1,"单选题","下列施工合同文件中，解释顺序优先的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","中标通知书",true,{"key":16,"text":17,"correct":18},"B","投标书",false,{"key":20,"text":21,"correct":18},"C","施工合同专用条款",{"key":23,"text":24,"correct":18},"D","规范","2020版教材P92-93 (1)合同协议书;(2) 中标通知书;(3) 投标函及投标函附录;(4) 专用合同条款;(5) 通用合同条款;(6) 技术标准和要求;(7)图纸;(8) 已标价的工程量清单;(9) 其他合同文件——经合同当事人双方确认构成合同的其他文件。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]