[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100068,779,1,"单选题","采用《简明施工合同》的工程，负责材料和设备的供应人通常为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","施工项目部",{"key":23,"text":24,"correct":14},"D","承包人","2020版教材P90 本题考查的是施工合同标准文本。由于简明施工合同适用于工期在12个月内的中小工程施工，是对标准施工合同简化的文本，通常由发包人负责材料和设备的供应，承包人仅承担施工义务，因此合同条款较少 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]