[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100056,779,1,"单选题","为了保证工程项目的建设质量达到预期的投资目的，实施过程必须遵循项目建设的内在规律，即坚持（ ）的程序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先勘察、后设计、再施工",true,{"key":16,"text":17,"correct":18},"B","先设计、后勘察、再施工",false,{"key":20,"text":21,"correct":18},"C","先设计、边勘察边施工",{"key":23,"text":24,"correct":18},"D","勘察、设计与施工同步进行","2020版教材P75-76 本题考核的是建设工程勘察设计合同。为了保证工程项目的建设质量达到预期的投资目的，实施过程必须遵循项目建设的内在规律，即坚持先勘察、后设计、再施工的程序。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]