[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100039":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100039,779,1,"单选题","根据九部委设计合同的规定，除专用合同条款另有约定外，发包人应在合同签订后（ ）内，确定发包人代表。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3天",false,{"key":16,"text":17,"correct":14},"B","7天",{"key":19,"text":20,"correct":21},"C","14天",true,{"key":23,"text":24,"correct":14},"D","28天","本题考查的是建设工程设计合同履行管理。设计合同中发包人代表的确定时间，是合同签订后14天内确定发包人代表。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]