[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100036,779,1,"单选题","设计人已完成全部设计任务，发包人的上级或设计审批部门对设计文件不审批，发包人应按合同规定( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","结清全部设计费",true,{"key":16,"text":17,"correct":18},"B","支付一半设计费",false,{"key":20,"text":21,"correct":18},"C","停止支付设计费",{"key":23,"text":24,"correct":18},"D","预留一定保证金后全部支付设计费","2020版教材P85-88 除专用合同条款另有约定外，发包人对于设计文件的审查期限，自文件接收之日起不应超过 14 天。发包人逾期未做出审查结论且未提出异议的，视为设计人的设计文件已经通过发包人审查。根据题干设计人已完成设计任务，故结清全部费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]