[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100021":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100021,779,1,"单选题","建设工程勘察中需要占用临时用地，位于道路、绿化或者其他市政设施内的临时占地，由（ ）向行政管理部门报建申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","勘察人",true,{"key":20,"text":21,"correct":14},"C","发包人或勘察人",{"key":23,"text":24,"correct":14},"D","发包人和勘察人","本题考查本题考查的是建设工程勘察合同履行管理。位于本工程区域内的临时占地，由发包人协调提供。位于道路、绿化或者其他市政设施内的临时占地，由勘察人向行政管理部门报建申请。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]