[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100008,779,1,"单选题","建设工程勘察合同履行管理中，关于监理人的说法错误的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","未经发包人批准，监理人无权修改合同",false,{"key":16,"text":17,"correct":14},"B","发包人可以根据工程建设需要确定是否委托监理人进行勘察监理",{"key":19,"text":20,"correct":21},"C","监理人的监理范围、职责权限和总监理工程师信息，应在通用合同条款中指明",true,{"key":23,"text":24,"correct":14},"D","如果委托监理，则监理人享有合同约定的权力，其所发出的任何指示应视为已得到发包人的批准","2020版教材P78-83 监理人：发包人可以根据工程建设需要确定是否委托监理人进行勘察监理。如果委托监理，则监理人享有合同约定的权力，其所发出的任何指示应视为已得到发包人的批准。监理人的监理范围、职责权限和总监理工程师信息，应在专用合同条款中指明。未经发包人批准，监理人无权修改合同。合同约定应由勘察人承担的义务和责任，不因监理人对勘察文件的审查或批准，以及为实施监理作出的指示等职务行为而减轻或解除。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]