[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100005":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100005,779,1,"单选题","除专用合同条款另有约定外，勘察人完成勘察工作所应遵守的法律规定，以及国家、行业和地方的规范和标准，均应视为在（）适用的版本。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基准日",true,{"key":16,"text":17,"correct":18},"B","保修期",false,{"key":20,"text":21,"correct":18},"C","开工日",{"key":23,"text":24,"correct":18},"D","竣工日","2020版教材P78-83 除专用合同条款另有约定外，勘察人完成勘察工作所应遵守的法律规定，以及国家、行业和地方的规范和标准，均应视为在基准日适用的版本。基准日之后，前述版本发生重大变化，或者有新的法律，以及国家、行业和地方的规范和标准实施的，勘察人应向发包人提出遵守新规定的建议。发包人应在收到建议后7 天内发出是否遵守新规定的指示。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]