[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1035758":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1035758,755,2,"多选题","关于发电厂、变电所接地装置的设置，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","接地装置应利用自然接地极，当其接地电阻符合要求时，可不另设人工接地极；",false,{"key":16,"text":17,"correct":18},"B","接地装置除利用自然接地极外，还应敷设以水平接地极为主的人工接地网；",true,{"key":20,"text":21,"correct":18},"C","接地装置应与架空线路的避雷线相连，且有便于分开的连接点；",{"key":23,"text":24,"correct":18},"D","对于3~IOkV变电所、配电所，当采用建筑物的基础作接地极且接地电阻又满足 規定值时，可不另设人工接地。","BCD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师供配电专业","建筑工程",0]