[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1035515":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1035515,755,2,"多选题","交流电流回路的设计有一些基本要求，下列正确的说法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在某些特殊情况下，保护装置和测量仪表必须共用一组电流互感器的同一个二次绕组上，此时测量仪表应接在保护装置之前；",false,{"key":16,"text":17,"correct":18},"B","对中性点直接接地系统，可按三相配置电流互感器，对中性点非直接接地系统，依 具体要求可按两相或三相配置；",true,{"key":20,"text":21,"correct":18},"C","电流互感器的二次回路不宜进行切换；",{"key":23,"text":24,"correct":18},"D","1lOkV及以上的电流互感器的额定二次电流宜选1","BCD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师供配电专业","建筑工程",0]