[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1035120":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},1035120,755,2,"多选题","TT系统采用熔断器或断路器作接地故障保护不能满足规定时间内动作的要求时， 可采取的措施有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用漏电电流保护器；",true,{"key":16,"text":17,"correct":18},"B","加大相导体截面；",false,{"key":20,"text":21,"correct":14},"C","降低变压器中性点接地电阻；",{"key":23,"text":24,"correct":14},"D","降低外露可导电部分的接地电阻。","ACD","",{"id":6,"name":28,"category":29,"favorite":30},"电气工程师供配电专业","建筑工程",0]