[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1034551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},1034551,755,2,"多选题","高压并联电容器装置断路的选择，除应符合断路器有关标准外，尚应符 合（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","关合时，触头弹跳时间不应大于2ms,且不应有过长的预击穿；10kV少油断路器的 关合预击穿时间不能超过3. 5ms ；",true,{"key":16,"text":17,"correct":14},"B","B开断时不应重燃；",{"key":19,"text":20,"correct":14},"C","应能承受关合涌流，以及工频短路电流和电容器涌流的联合作用；",{"key":22,"text":23,"correct":14},"D","每天段切超过三次的断路器，应具备频繁操作性。","ABCD","",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师供配电专业","建筑工程",0]