[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1034353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1034353,755,2,"多选题","采用需要系数法求某办公楼的计箅负荷.已知数据见表3-4。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该项目的总需要系数约为（）。",false,{"key":16,"text":17,"correct":14},"B","0.34;",{"key":19,"text":20,"correct":14},"C","0.44； C 0.54；",{"key":22,"text":23,"correct":24},"D","0.64。",true,"",{"id":6,"name":27,"category":28,"favorite":29},"电气工程师供配电专业","建筑工程",0]